The new Town Hall Cotillas Towers, being built across the street of the village D'Stoup, tuck and the final stretch of his building after a complicated journey.
And what makes the hand of the new contractor, "Ferrovial Agroman, SA", after the termination of the contract that was forced to make the City Council awarded Torreño with initial works, the company "Ploder."
The latter, who had been designated to perform this construction valued at more than six million euros, left the building due to financial problems after certifying 93% of the building.
Now, the remaining 7% of the work has been awarded "Ferrovial Agroman, SA worth over half a million euros and involve mainly the urban environment and the completion of the external spaces and interior of the building.
And is that the company "Ploder" presented last January from creditors voluntary basis, so that the Consistory Torreño was forced to terminate the contract.
A procedure which, after the regulatory process, took place last July 23 at a plenary session which also approved the start of file damage claims to the company.
Works that the mayor of Las Torres de Cotillas, Domingo Coronado, visited on Friday morning September 17, accompanied by the Councillor for Urbanism of the municipality, Yolanda Muñoz, other members of the local corporation, municipal technicians staff from the new contractor.
"We want to be ready soon," stated Coronado, which has been proposed that the remaining work "can last about four months."
"I do not want the opening of the new Town Hall is related to the elections next year. This was an important point in my electoral program of 2007 which, unfortunately and unintentionally by the City Torreño, has been delayed "has affected the mayor Torreño.
By modernity
The new Town Hall will have a total area of 7,832 meters square of floor space, a building that will be distributed in six plants (two type basement) and that will bring together the all municipal services to provide better service to citizens.
The new City Hall will replace the existing, built in 1970, and has remained small due to the increasing population of the municipality, and the assumption of new powers have also led to an increase in staff, so it was necessary to expand headquarters Hall.
The project, developed by a team of architects Murcia AD HOC MSL, includes the construction of this building in the neighborhood of a recently developed space that will also include parks and gardens, shopping areas and housing and 142 parking spaces.
Source: Ayuntamiento de Las Torres de Cotillas